How to record stage progress and read the delivery projection

You will record how far a construction stage has got, see what that does to project completion, earned value and the next invoice, and read the projected finish date and its risk badge.

Who it is forSite manager or project managerTime10 minutesProductBuildFlowLevelIntermediate

Before you start

Steps

1

Open the Progress page

Open Delivery › Projects & sites › Projects, open the project, then The build › Progress. At the top is the Delivery projection, then Delivery dates, then Stage progress with one row per stage.

Progress and delivery page with the projection, dates and stage rows
Progress and delivery page with the projection, dates and stage rows
2

Open the stage you want to update

Click the stage row. It opens to show its progress bar, the Record progress button and the Update history.

Structure stage expanded with its record button and history
Structure stage expanded with its record button and history
3

Record the percent

Click Record progress. Type a whole number from 0 to 100 in Percent complete (the box shows the current value). Fill Progress as of (optional) with the day you saw the work if you are entering it late; leave it empty for today. A future date is refused with "The date cannot be in the future." Add a Note (for example "Ground floor slab shuttering done, steel fixed.") and click Save progress.

Record stage progress dialog with 35 percent and a note
Record stage progress dialog with 35 percent and a note
4

See what the save changed

The stage becomes In progress and the project header shows the stage percent and Complete (by value) with two decimals (here 32.37%). The delivery projection and the command bar's earned value (for example Rs 3,796,072 earned so far) update at once, without reloading the page.

Project header showing 35 percent and 32 percent complete by value
Project header showing 35 percent and 32 percent complete by value
5

Check the history

Every save is listed newest first with its save time, the Progress as of day, your note and a chip: Visible to customer on portal or Internal only. History cannot be edited.

Update history with the note and customer visibility chip
Update history with the note and customer visibility chip
6

Understand completion by value

Stages count by their share of the contract value, not equally. With Site prep and Foundation at 100% and Structure at 35%, the project is 32.37% complete. A plain average of the eight stages would show 29.4%.

Header showing complete by value
Header showing complete by value
7

Read earned value

Open The money › Cost. Earned value is the contract value before tax times the exact share complete: Rs 3,796,072 here. Profit says "Too early to call" until costs are recorded.

Cost tab with earned value and work complete
Cost tab with earned value and work complete
8

Check the actual dates

Open The build › Stages. The Actual column fills itself: the first progress above 0% (or the first crew deployment) stamps the start, reaching 100% stamps the end, on the Progress as of day (today when it is empty). Nobody types them.

Stages tab showing actual start and end dates
Stages tab showing actual start and end dates
9

Bill the finished stage

When a stage is at 100% and the earlier draws are billed, the project header offers Bill Stage: Foundation (Rs 1,443,120). The draw's due date becomes the Progress as of day plus the customer's credit term (here Net 30, so 10-Dec-2026 for progress seen on 10 Nov) instead of a tentative date.

Payment tab with the draw schedule and Bill Stage button
Payment tab with the draw schedule and Bill Stage button
10

Read the delivery projection

Planned delivery is the committed date. Tentative delivery is projected from the pace of the first unfinished stage plus the planned length of every later stage. Delay (days) is the gap, never below zero. The badge reads On track, At risk, Late, Delivered or Dates not set.

Delivery projection showing planned and tentative delivery, delay and risk
Delivery projection showing planned and tentative delivery, delay and risk
11

When plan dates are missing

If stages have no planned dates the page shows Dates not set and a note such as "3 stage(s) have no planned dates, so delivery cannot be projected yet". Set the dates on the Stages tab.

Projection with the missing dates note
Projection with the missing dates note

Check it worked

  • The stage row shows the new percent and status, and Last update shows the day you saved it.
  • Complete (by value) in the header matches the Cost tab's Work complete (by value).
  • The Projects list shows the tentative delivery date and risk badge for the project, and the site wallboard shows the same numbers.
  • Staff get a bell notification such as "Stage "Foundation" … is now 100% complete."

Common mistakes

MistakeWhat you seeFix
Saving with the percent box emptyThe message "Enter a whole number from 0 to 100."Type the real percent
Entering Friday's visit on Monday without a dateThe history and the stage dates carry Friday only if you fill Progress as of; otherwise MondayFill Progress as of with the day you saw the work
Waiting for Bill StageThe button does not appearBring the stage to 100% and invoice the earlier draws first
Reading 32.37% as a plain averageThe numbers differ from your own sumsCompletion counts each stage by its contract value

Quick reference

ItemMeaning / rule
Status100% = Completed; above 0 = In progress; 0 = Not started; On hold is kept
Completion by valueSum of (stage value x percent) divided by the sum of stage values
Earned valueContract value before tax x exact completion percent
Tentative deliveryPace of the first unfinished stage plus planned lengths of later stages
Delay (days)Tentative minus planned delivery, never below zero
RiskDates not set, On track, At risk, Late, Delivered

Frequently asked questions

Does recording progress create an invoice? No. It only unlocks the draw and sets its due date. You issue the invoice from the header button or the Payment tab.

Can I reopen a stage? Yes. Record a lower percent: the stage returns to In progress and its end date is cleared. Invoices already issued stay.

Does the delivery risk change my contract? No. It is advice only and does not move crews, stage dates or the contract.

Do this in BuildFlow

BuildFlow runs this whole workflow. See what BuildFlow does and what it costs, or browse all step-by-step guides.